"Draft
Only - Approval Pending"
M I N U T E S
Select School Facilities Committee
University
of Wyoming Outreach Center September
26, 2005
951
North Poplar Casper, Wyoming
PRESENT: Senator Hank Coe,
Co-Chairman;
Representative Del McOmie, Cochairman;
Senators Jim Anderson and John Hines;
Representatives Patrick Goggles, Debbie Hammons and Mick
Powers.
Other Legislators In Attendance: Senator Grant Larson and
Representatives Bob Brechtel and Randall Luthi.
School Facilities Commissioners: Jeff Marsh, Chairman, Richard Gilpatrick, Ralph Goodson and
Jeffrey Carrier.
Legislative Service Office: Dave Nelson, Brenda Long, Matt
Sackett and Joe Rodriguez.
Others: See attached
Appendix A.
ABSENT: Senators
Mike Massie and Kathryn Sessions and Representative Alan Jones.
* *
* * *
Senator
Hank Coe, Select Committee Cochair, called the meeting to order at 8:35
a.m. Select Committee Staff Dave Nelson
conducted roll call with three members absent.
There was no agenda specified as the meeting was considered a working
session.
School Facilities Commission.
Cochair Coe welcomed the School Facilities
Commission. Commission Director Bubba
Shivler introduced School Facilities Commission members and staff in
attendance. CoChair Coe announced the
Select Committee would be accepting a report from the School Facilities
Commission and that public comment on Select Committee forwarding of report
recommendations would be taken at a subsequent Select Committee meeting.
Biennial Plan
Submittal. Commission
Director Shivler reported the School Facilities Commission is recommending
two-year plans be submitted by July 1 of each odd-numbered year to coincide
with the state funding cycle. On
alternate years, the Commission is recommending assessments be done of school
buildings to indicate building progress.
This new approach would eliminate confusion, save the state
approximately $700,000 on even number years in professional facility planning
expertise, save districts valuable staffing time, allow Commission staff to
conduct building assessments in house on even numbered years and would be less
demanding on Commission members. Issue
summaries were distributed during subsequent discussion and are attached as
Appendix B and Appendix C.
Nancy Thomson, Commission staff, stated Commission
recommendations would allow for some flexibility to districts to change the
scope of their projects on out years through the supplemental budget process.
Contracting Directly
with Project Architect and Development of Standardized Building Plans. Director Shivler reported
school construction projects are coming in as much as 50% over budget. The Commission suggests that the majority of
the cost escalations are coming from the design phase of building projects, and
is requesting legislation specifying the Commission may contract directly with
the project architect. Director Shivler
stated that districts would continue to provide valuable input during the
design process, but the additional directive would provide the Commission the ability
to maintain some control on total project costs.
Director Shivler also discussed a recommendation to
establish standardized school designs. He
suggested this method would work well with elementary schools but may be more
difficult to implement at the middle and high school level. The main focus is to ensure schools are
educationally suitable. An issue
summary was distributed and is included as Appendix D. Cochair Coe inquired if the Commission had
the ability to currently proceed in this manner. Mr. O’Donnell responded current statutory provision is vague. Cochair Coe instructed Select Committee
staff to draft legislation for consideration at the next Select Committee meeting.
Representative Powers expressed concern that the
Commission currently has sufficient control with respect to school building
projects, and suggested local control has been eliminated from the grade
configuration and building site project decisions. Director Shivler agreed that the Commission is resistant to
district demands since law requires it to get district buildings to capacity
standards. Commission Chairman Marsh
followed up Director Shivler’s comments by stating the statutes also allow the
Commission to consolidate across district lines, with the consultation of the
Select Committee and the legislature.
Chairman Marsh stated the mission of the Commission is to proceed in the
building remediation process with due diligence through the most cost effective
means. He also pointed out that although
the population in Wyoming is rising, the school age population is declining.
Commission Authority
to Enforce Value Engineering Recommendations. Director Shivler explained that
currently the value engineering process for any school building project is done
in two phases: 10% schematic design phase and 35% building design phase. Presently, the districts are considering but
not following the value engineering recommendations. The Commission is requesting statutory authority to enforce value
engineering recommendations. An issue
summary was distributed and is attached at Appendix E.
The Select Committee and School Facilities
Commission held discussion on the type of designs that are causing building
projects to exceed budgeted amounts and the possibility of modifying the process
to allow the construction industry sufficient opportunity to stabilize.
Consolidation
of Facilities. Director
Shivler referenced Big Horn County School Districts #1 and #2 as potential
candidates for consolidation under W.S. 21‑15‑117. Expanding, Director Shivler pointed out
Lovell has a high school that is declining in enrollment but pointed out a new
school is being completed in Cowley. Both
locations are separated by not more than 4.5 miles. Educational specialists have
advised the Commission that high schools can be too small and that schools less
than 200 students present size issues.
Discussion also focused on Big Horn County School
Districts #3 and #4 and Uinta County School Districts #4 and #6. It was noted communities within these districts
are currently transcending district boundaries for various school programs and
activities.
The Select Committee and the Commission concluded
discussion by identifying the impact of consolidation the respective communities
and incentives for communities to consolidation themselves rather than mandates
imposed by the Commission or the legislature.
An issue summary was distributed during this discussion and is included
as Appendix F.
Off Site
Developments. Director Shivler brought to the attention of the Select
Committee the fact that the Commission is not currently providing funds to
school districts for off-site developments such as sidewalks, curb and gutter,
street lights, traffic lights, intersection improvements and water and sewer
lines. These expenditures are becoming
substantial to impacted communities.
Recently Cheyenne was quoted $6.2 million for sewer and water lines and
street infrastructure necessary for the completion of a new school. The Commission recommends the establishment
of a state level funding mechanism for this purpose which is outside of the
Commission's jurisdiction.
Select Committee members suggested several other
programs currently exist for these communities to pursue in funding necessary
infrastructure and Representative Goggles request Select Committee staff to
provide a summary of current programs. The
issue summary for this topic is attached at Appendix G.
Alternative
Schools. Director
Shivler advised that further information and clarification is required as to
parameters and criteria for alternative high schools. State Superintendent McBride and the Department of Education is
working on the development of this information and upon completion, the
Commission will move forward in providing facility standards to meet the needs
of district alternative high school facilities. The issue summary is included at Appendix H.
Vocational
Education. Director Shivler reported that vocational education subject is a
similar issue as alternative schools, and that the state needs to develop
policy for vocational education programs offered by school districts. Districts are not satisfied by the space
provided for vocational education programs within facility standards. The State Superintendent and the Department
of Education are aware of this matter.
The need for technical education was discussed as
well as the option of establishing regional vocational education facilities and
cooperating with community colleges in provision of career/vocational programs. The issue summary is included as Appendix I.
Teacherages. Director Shivler stated
districts are requesting funding for new teacherage facilities at remote school
locations. Currently Commission provides major maintenance to maintain existing
teacherages; however, there are no guidelines for new teacherages. The Commission requests guidance from the
Select Committee. Select Committee members
requested Commission staff provide additional information on teacherages. An issue summary is included as Appendix J.
State Agency
Leases and Major Maintenance Payments. Director Shivler explained
as the Commission begins to reduce excess square footage in districts, many
communities are requesting to lease excess space at a reduced cost that does
not compensate districts for space maintenance. Further, the communities suggest that the state maintain these
facilities. The Commission requests the
Select Committee forward legislation to encourage districts to reduce
inventories and to clarify payment of maintenance costs for leased district
facilities. An issue summary is attached
at Appendix K.
Budget. Director Shivler reported following
completion of the district five year plan review, the Commission estimates a
budget need of roughly $500 to $600 million over this period of time. Teresa
Kunkel, Commission staff, added that to remedy some of the problems that have
arose this past biennium, the Commission is requesting inflationary funds over two
periods, 15% for the prior biennial period and 15% for the current biennium. These funds will enable projects to move
forward. An additional amount will be
request by the Commission to cover reallocation costs built in at 10% to 15% of
the construction budget, which will be designed to allow the Commission to
continue to proceed with district projects in a timely manner.
Commission members also discussed additional positions
requested in the budget, the cost savings generated by conducting building
condition assessment reviews by Commission staff, budget contingency amounts
and project reallocations. Ms. Kunkel
explained project changes or reallocations from what was presented in the original
budget, and copies of information outlining project changes and re-allocation were
distributed. Materials distributed are
attached at Appendix L and Appendix M.
Cochair Coe directed attention to the LSO issue
brief on school construction costs and issues, previously distributed to Select
Committee members. A copy is attached
at Appendix N.
Adjournment.
There
being no further business, Cochair Coe adjourned the Select Committee at 12:04
p.m.
Respectfully
submitted,
__________________________ __________________________
Senator
Hank Coe, Representative Del
McOmie,
Select
Committee CoChair Select Committee
CoChair